Thursday, May 21, 2020

RATE ANALYSIS FOR PLAIN CEMENT CONCRETE PCC 1:4:8

Providing & laying PCC (1:4:8) Manually

Providing and laying PCC 1:4:8 in wall trenches, below Plinth, below flooring, outside flooring and column footing pits etc., wherever specified using sand, 40mm and down size aggregate including cleaning, sub grade preparation & levelling including machine mixing, tamping, curing, etc., and shuttering if necessary complete at all heights and depths as instructed.

Sl. No. Description Unit Quantity  Rate
 (Rs.) 
 Amount.
(Rs.) 
A) Materials:        
1 Cement Bags 4.440             350.00            1,554.00
2 M Sand Cum 0.460          2,118.90               974.69
3 Aggregate Cum 0.920             988.82               909.71
  Sub-Total of Material (M)                 3,438.41
           
B) Labour:         
1 Labour Charges Rs.15/- per cft                     529.73
  Sub-Total of Labour (L)                    529.73
  Total (M+L)                 3,968.13
C) Add for T & M   2.00%                  79.36
D) Water & Electricity    2.00%                  79.36
E) Watstage   5.00%                171.92
  Total Amt.                 4,298.78
  Cost Per 1 Cum (Rs.)                 4,298.78
  Cost Per 1 Cft (Rs.)                    121.73